It's Time to Start Framing
Part 1, Part 2, Part 3, Part 4, Part 5, Part 6, Part 7, Part 8
We had a tight schedule to maintain. In 2 days, the framers would come in and put up the house. They started with the basement walls, beams, and post:
The floor joists then are installed. In the meantime we thoroseal the outside of the foundation to protect from water:
Subfloor is put down along with framing the first wall:
The first wall - the front of the house:
While we have an 8 foot hole - we bury 3/4 pex as a potential heat sink for the under floor randiant floor heating system (possible "air conditioning"):
The last wall us put in place:
With the floor joists down and the basement wall protected with thoroseal, we are now able to start back filling the 8 foot deep moat around the house:
So far we are only a few days into framing the house!